Main Street Revitalization
Description
The Main Street Revitalization (MSR) Project is the full reconstruction of about 4,000 linear feet of Winooski’s Main Street, a Principal Arterial with an AADT of about 15,000. The project will improve safety, accessibility, and mobility for all modes of transportation through the corridor; replace vital water, sewer, and stormwater infrastructure; and accommodate stable growth along the corridor by eliminating physical barriers (e.g., overhead utilities) and improving the streetscape and landscape environment.
Updates
March 28, 2023 - Current Progress
The Right of Way Acquisition process is complete. City staff are performing a final review of contract documents and working to meet all remaining requirements of the project funders. The Main Street Revitalization Project bid advertisement is targeted for May 2023. If the contract is awarded, construction would likely begin sometime in July. Updates with specific details about construction impacts would be provided to the public starting in June or July, and will continue through the three-year construction project.
Previous Updates
- February 21, 2023: City Council Update
- February 6, 2023: City Council Update and Bond Resolutions
- April 4, 2022: RAISE Grant Application Approval
- July 19, 2021: City Council Update and RAISE Grant Application Approval
- March 15, 2021: City Council Update
- September 8, 2020: City Council Update & Presentation
News and Public Meetings
- Leahy, Sanders, and Welch: USDA Makes $8.5 Million Investment in Winooski Main Street Revitalization
- City of Winooski Awarded VTrans Bicycle and Pedestrian Grant
- Channel 17: In the World of Winooski - The Main Street Revitalization Project
- Local 22: Revitalizing Winooski’s Main Street, Special Bond Vote Nears
- Channel 17: Joint Planning Commission and Public Works Commission Meeting
- WCAX: Major Development Continues in Winooski
- Presentation to the Planning and Public Works Commissions 4.12.18
- Presentation to the Winooski City Council 3.19.18
- Main Street Revitalization Bond Vote - Town Meeting Day Presentation March 2018
- Alternatives Presentation for Winooski City Council 1.10.18
- Local Concerns Presentation 11.29.17
Project Contacts
General Questions: mainstreet@winooskivt.gov
Jon Rauscher, Director of Public Works: jrauscher@winooskivt.gov
802 655 6410 ext. 18
Ryan Lambert, City Engineer: rlambert@winooskivt.gov
Related Documents
- Project Area
- 90% Design Documents - Plans
- Right of Way Plans - Latest Draft
- Environmental Report
- Preliminary Engineering Report
- RAISE Grant Letter
- Drinking Water Conditional Approval
- Clean Water FSNI and Facilities Plan Approval
- FHWA NEPA CatEx
- See addition documents via the CCRPC Project Page
- Northern Border Regional Commission Notice of Availability